Q 5. How much will your plant spend for machinery/equipment related to screw machining in 2009?
$2,601,857,551
(Total projected production machinery/equipment expenditure.)
Q 6. What percentage of your capital spending equipment budget will be spent on?
|
2009 |
2008 |
2007 |
2006 |
2005 |
New |
59.1 |
59.9 |
59.1 |
53.7 |
51.8 |
Used |
28.7 |
29.7 |
30.0 |
32.0 |
35.3 |
Rebuilt |
12.2 |
10.4 |
10.9 |
14.3 |
12.9 |
| Total |
100.0 |
100.0 |
100.0 |
100.0 |
100.0 |